04.02.2025

PRIDE: Glazing Completed in Sections 7 & 8

Facade installation works are progressing actively at PRIDE, a premium residential development. Glazing has now been fully completed in Sections 7 and 8, while window installation in Section 10 has reached the 11th floor.

In Sections 7, 8, and 9, finishing works have commenced inside the apartments, including plastering, convector installation, and drywall partition assembly.

In communal areas, rough finishing works are now 89% complete, with wall plastering and floor screeding finished across all sections. In Sections 4 and 5, floor tiling has been completed.

Lift installation is now 78% complete, with 14 out of 26 lifts undergoing testing and commissioning.

The first phase of the PRIDE family-oriented premium residential development is scheduled for completion by late 2025.