01.10.2022

Monolithic works in Ostankino Business Park completed in Building 4

The monolithic frame has been erected in Building 4 of Ostankino Business Park. The façade subsystem and glazing are now being actively assembled.

In buildings 2 and 3, the finishing works are being completed before the commissioning of the buildings: landscaping and planting of greenery. Inside the buildings, workers are completing the finishing works of the lift lobbies and staircases.

In Block 5, the monolith is being performed on 11-12 floors. The works on waterproofing and insulation of the plinth are already finished, and the backfilling of the excavation slots is in progress. The builders have started laying the exterior walls at the end of the building.